SENTALICA // Entity Performance Scorecard

Kotido DLG

STATUS: Live Data
OVERALL PCI GRADE:C (68/100)
NATIONAL RANK:Top Sector Tier
CATEGORY:Local Government
Core Performance Dashboard Metrics
Transparency Score
60/100[Excellent]
Average Procurement Cycle
54 Days[Med]
Contract Performance
74%[On-Time]
Average Payment Latency
51 Days[Arrears Flag]
Average Bidders per Tender
5.2SME Scale
Appeals Rate
0.6%[Low]
1. Historical Winner ConcentrationTop 3: 56% Ratio
1.
Energoinvest DD7 active contracts
UGX 484B22% Share
2.
Prism Construction Ltd2 active contracts
UGX 484B22% Share
3.
Roko Construction1 active contracts
UGX 264B12% Share
2. Top Disqualification Traps in this Agency
Invalid Manufacturer Authorization FormIdentified Rejection Risk Pattern
44%
Failed SCADA Grid Protocol System TestsIdentified Rejection Risk Pattern
33%
Class 3 Address Errors on Tax Clearance (TCC addressed to wrong entity)Identified Rejection Risk Pattern
21%
Active Auditor General (OAG) Warnings
OAG
[OAG-KOTIDO-01] Systemic Delayed Invoice Settlements

Over 110 days median payment delay leading to contractor abandonment of remote project sites.

OAG
[OAG-KOTIDO-02] Substation Right-Of-Way Hostility

Social-environmental blockades delayed grid tie-in by 180 days.

Fiduciary compliance screening platform  •  Sentalica 2026
Audit Draft Bid for this MDA