SENTALICA // Entity Performance Scorecard

Ministry of Information, Communications Technology and National Guidance

STATUS: Live Data
OVERALL PCI GRADE:B (70/100)
NATIONAL RANK:Top Sector Tier
CATEGORY:Ministry
Core Performance Dashboard Metrics
Transparency Score
66/100[Excellent]
Average Procurement Cycle
48 Days[Med]
Contract Performance
72%[On-Time]
Average Payment Latency
51 Days[Arrears Flag]
Average Bidders per Tender
3.2SME Scale
Appeals Rate
0.6%[Low]
1. Historical Winner ConcentrationTop 3: 54% Ratio
1.
Prism Civil Works1 active contracts
UGX 65B26% Share
2.
Chongqing International Corp (CICO)2 active contracts
UGX 40B16% Share
3.
Energoinvest DD1 active contracts
UGX 30B12% Share
2. Top Disqualification Traps in this Agency
Inadequate Experience in Similar Bulk WorksIdentified Rejection Risk Pattern
46%
Lapsed professional liability credentialsIdentified Rejection Risk Pattern
32%
Failed SCADA Grid Protocol System TestsIdentified Rejection Risk Pattern
20%
Active Auditor General (OAG) Warnings
OAG
[OAG-MOICT-01] Terminal Expansion Delayed Milestones

Overlapping civil engineering delays in luggage handling system handovers.