Ministry of Works and Transport

STATUS: Live Data
OVERALL PCI GRADE:B (79/100)
NATIONAL RANK:Top Sector Tier
CATEGORY:Ministry
Core Performance Dashboard Metrics
Transparency Score
84/100[Excellent]
Average Procurement Cycle
45 Days[Med]
Contract Performance
83%[On-Time]
Average Payment Latency
50 Days[Arrears Flag]
Average Bidders per Tender
6.2SME Scale
Appeals Rate
0.5%[Low]
1. Historical Winner ConcentrationTop 3: 54% Ratio
1.
Kigezi Builders & Co1 active contracts
UGX 93B27% Share
2.
Ambitious Construction Co1 active contracts
UGX 55B16% Share
3.
Ankole Civil Contractors3 active contracts
UGX 38B11% Share
2. Top Disqualification Traps in this Agency
Class 2 Statutory Substitution Errors (NSSF app instead of Certificate)Identified Rejection Risk Pattern
42%
Average Annual Construction Turnover DeficitIdentified Rejection Risk Pattern
32%
Failed SCADA Grid Protocol System TestsIdentified Rejection Risk Pattern
22%
Active Auditor General (OAG) Warnings
OAG
[OAG-MOWT-01] Unaccounted Project Advances

OAG identified unretired project advances to contractors exceeding statutory thresholds.

OAG
[OAG-MOWT-02] Delayed Municipal Streetlights Installation

Administrative delay on street-lighting grid switch connections.

Fiduciary compliance screening platform  •  Sentalica 2026