SENTALICA // Entity Performance Scorecard

Sembabule DLG

STATUS: Live Data
OVERALL PCI GRADE:C (64/100)
NATIONAL RANK:Top Sector Tier
CATEGORY:Local Government
Core Performance Dashboard Metrics
Transparency Score
71/100[Excellent]
Average Procurement Cycle
57 Days[Med]
Contract Performance
65%[On-Time]
Average Payment Latency
49 Days[Arrears Flag]
Average Bidders per Tender
7.2SME Scale
Appeals Rate
0.9%[Low]
1. Historical Winner ConcentrationTop 3: 59% Ratio
1.
Energoinvest DD6 active contracts
UGX 177B24% Share
2.
CMD Civil Works4 active contracts
UGX 154B21% Share
3.
Nile Civil Contractors2 active contracts
UGX 103B14% Share
2. Top Disqualification Traps in this Agency
Average Annual Construction Turnover DeficitIdentified Rejection Risk Pattern
46%
Failure to provide structural concrete safety test logsIdentified Rejection Risk Pattern
29%
Failed Technical Specification ClearanceIdentified Rejection Risk Pattern
25%
Active Auditor General (OAG) Warnings
OAG
[OAG-SEMBAB-01] Delayed Pipe Commissioning

Minor civil engineering delays in Eastern Uganda sewer linkages.

OAG
[OAG-SEMBAB-02] Irregular Contract Variations

OAG flagged contract variations processed without proper change-order authorization.